Abstract:
The 10 MeV accelerator-driven subcritical system (ADS) Injector-I test stand at Institute of High Energy Physics (IHEP) is a testing facility dedicated to demonstrate one of the two injector design schemes [Injector Scheme-I, which works at 325 MHz], for the ADS project in China. The Injector adopted a four vane copper structure RFQ with output energy of 3.2 MeV and a superconducting (SC) section…
▽ More
The 10 MeV accelerator-driven subcritical system (ADS) Injector-I test stand at Institute of High Energy Physics (IHEP) is a testing facility dedicated to demonstrate one of the two injector design schemes [Injector Scheme-I, which works at 325 MHz], for the ADS project in China. The Injector adopted a four vane copper structure RFQ with output energy of 3.2 MeV and a superconducting (SC) section accommodating fourteen \b{eta}g=0.12 single spoke cavities, fourteen SC solenoids and fourteen cold BPMs. The ion source was installed since April of 2014, periods of commissioning are regularly scheduled between installation phases of the rest of the injector. Continuous wave (CW) beam was shooting through the injector and 10 MeV CW proton beam with average beam current around 2 mA was obtained recently. This contribution describe the results achieved so far and the difficulties encountered in CW commissioning.
△ Less
Submitted 15 May, 2017;
originally announced May 2017.
-
RF modulation studies on the S band pulse compressor
Authors:
G. Shu,
F. Zhao,
S. Pei,
O. Xiao
Abstract:
An S band SLED-type pulse compressor has been manufactured by IHEP to challenge the 100 MW maximum input power, which means the output peak power is about 500 MW at the phase reversal time. In order to deal with the RF breakdown problem, the dual side-wall coupling irises model was used. To further improve the reliability at very high power, amplitude modulation and phase modulation with flat-top…
▽ More
An S band SLED-type pulse compressor has been manufactured by IHEP to challenge the 100 MW maximum input power, which means the output peak power is about 500 MW at the phase reversal time. In order to deal with the RF breakdown problem, the dual side-wall coupling irises model was used. To further improve the reliability at very high power, amplitude modulation and phase modulation with flat-top output were taken into account. The RF modulation studies on an S-band SLED are presented in this paper. Furthermore, a method is developed by using the CST Microwave Studio transient solver to simulate the time response of the pulse compressor, which can be a verification of the modulate theory. In addition, the experimental setup was constructed and the flat-top output is obtained in the low power tests.
△ Less
Submitted 27 May, 2015;
originally announced May 2015.
-
Impedance Measurements of the Extraction Kicker System for the Rapid Cycling Synchrotron of China Spallation Neutron Source
Authors:
Liangsheng Huang,
Sheng Wang,
Yudong Liu,
Yong Li,
Renhong Liu,
Ouzheng Xiao
Abstract:
The fast extraction kicker system is one of the most important accelerator components, whose inner structure will be the main source of the impedance in the RCS. It is necessary to understand the kicker impedance before its installation into the tunnel. The conventional and improved wire methods are employed for the benchmarking impedance measurement results. The simulation and measurements confir…
▽ More
The fast extraction kicker system is one of the most important accelerator components, whose inner structure will be the main source of the impedance in the RCS. It is necessary to understand the kicker impedance before its installation into the tunnel. The conventional and improved wire methods are employed for the benchmarking impedance measurement results. The simulation and measurements confirm that the window-frame ferrite geometry and the end plate are the important structures causing the coupling impedance. The total impedance of the eight modules systems is determined by the scaling law from the measurement and the impedance measurement of the kicker system is summarized.
△ Less
Submitted 7 April, 2015;
originally announced April 2015.